Question 1

Rounding non-integer solution values up to the nearest integer value will result in an infeasible solution to an integer linear programming problem.

Answer

True

False

2 points 

Question 2

In a mixed integer model, some solution values for decision variables are integer and others are only 0 or 1.

Answer

True

False

2 points 

Question 3

If we are solving a 0-1 integer programming problem, the constraint x1 ? x2 is a conditional constraint.

Answer

True

False

2 points 

Question 4

If we are solving a 0-1 integer programming problem with three decision variables, the constraint x1 + x2 ≤ 1 is a mutually exclusive constraint.

Answer

True

False

2 points 

Question 5

If we are solving a 0-1 integer programming problem with three decision variables, the constraint x1 + x2 + x3 ≤ 3 is a mutually exclusive constraint.

Answer

True

False

2 points 

Question 6

A conditional constraint specifies the conditions under which variables are integers or real variables.

Answer

True

False

2 points 

Question 7

In a capital budgeting problem, if either project 1 or project 2 is selected, then project 5 cannot be selected. Which of the alternatives listed below correctly models this situation?

Answer

x1 + x2 + x5 ? 1

x1 + x2 + x5 ?1

x1 + x5 ≤ 1 1, x2 + x5 ≤ 1 

x1 – x5 ≤ 1 1, x2 – x5 ≤ 1 

2 points 

Question 8

If we are solving a 0-1 integer programming problem, the constraint x1 + x2 = 1 is a __________ constraint.

Answer

multiple choice

mutually exclusive

conditional

corequisite

2 points 

Question 9

You have been asked to select at least 3 out of 7 possible sites for oil exploration. Designate each site as S1, S2, S3, S4, S5, S6, and S7. The restrictions are:

Restriction 1. Evaluating sites S1 and S3 will prevent you from exploring site S7.

Restriction 2. Evaluating sites S2 or

S4 will prevent you from assessing site S5.

Restriction 3. Of all the sites, at least 3 should be assessed.

Assuming that Si is a binary variable, the constraint for the first restriction is

Answer

S1 + S3 + S7  ≥ 1

S1 + S3 + S7 ≤1

S1 + S3 + S7 = 2

S1 + S3 + S7 ≤ 2

2 points 

Question 10

The Wiethoff Company has a contract to produce 10000 garden hoses for a customer. Wiethoff has 4 different machines that can produce this kind of hose. Because these machines are from different manufacturers and use differing technologies, their specifications are not the same.

Write the constraint that indicates they can purchase no more than 3 machines.

Answer

Y1 + Y2 + Y3+ Y4 ≤ 3

Y1 + Y2 + Y3+ Y4 = 3

Y1 + Y2 + Y3+ Y4 ≥ 3

none of the above

2 points 

Question 11

If we are solving a 0-1 integer programming problem, the constraint x1 = x2 is a __________ constraint.

Answer

multiple choice

mutually exclusive

conditional

corequisite

2 points 

Question 12

If we are solving a 0-1 integer programming problem, the constraint x1 ≤ x2 is a __________ constraint.

Answer

multiple choice

mutually exclusive

conditional

corequisite

2 points 

Question 13

In a 0-1 integer programming model, if the constraint x1-x2 = 0, it means when project 1 is selected, project 2 __________ be selected.

Answer

can also

can sometimes

can never

must also

2 points 

Question 14

If the solution values of a linear program are rounded in order to obtain an integer solution, the solution is

Answer

always optimal and feasible

sometimes optimtax chapter18-1,Accounting,$20.00,

Get a Unique Answer HERE or Order a Similar Paper

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Place Order” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order