Chat with us, powered by LiveChat Small Construction Project Earned Value Case Study | WriteDemy

Question Description

Small Construction Project Earned Value Case Study

Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below.

ID

Activity

Original Duration (days)

Actual Duration

(days)

Actual Start Date

Actual Finish Date

%

Complete

Original

Budget

Actual

Budget

10

Site Prep

8

9

2/27

4/26

100

$500,000

$600,000

20

Substructure

12

11

5/1

7/18

100

$1,500,000

$1,350,000

30

Super Substructure

18

–

7/20

–

75

$2,000,000

$1,450,000

40

Exterior

6

–

–

–

0

$400,000

–

50

Interior

14

–

8/31

–

50

$1,800,000

$1,000,000

60

Services

10

–

–

–

0

$1,000,000

–

70

Cleanup

4

–

–

–

0

$200,000

Question 1: Forecast the duration of the activities that are currently in progress assuming their current rate of progress will continue till the end of the project. Find out the remaining duration as per the forecasted duration.

Step 1 – Determine activities in progress (ID 30 and ID50) – Less than 100% complete

Step 2 – Calculate actual duration from activity start date to status date for each activity in progress. The remaining duration calculation must be computed using the % of work completed to date.

ID 30 – Activity 30 Super Substructure

Actual Duration up to status date = ____#weeks to status date (Activity start date -7/20) thru (Project Status Date – 10/28)

% of work Complete = 75% (From Chart above)

New Duration at 100% = 100 * _ #weeks to status date / 75 (% of work complete) = ______#weeks to complete 100%

Remaining Duration at 25% = _____weeks to complete 100% – #weeks to status date __________

ID 50 – Activity 50 Interior

Actual Duration up to status date = ______#weeks to status date (Activity start date -8/31) thru (Project Status Date – 10/28)

% of work Complete = 50% (From Chart above)

New Duration at 100% = 100 * _____#weeks to status date / 50 (% of work complete) = ______ #weeks to complete 100%

RemainingDuration at 50% = _____#weeks to complete 100% – #weeks to status date ___________

Question 2: Calculate the Planned Value (BCWS) based on the original budget, the original duration, and the number of weeks between the planned early start date and the status date (October 28th for the activities that are in progress. This calculation will provide the amount of money the project has spent up to October 28th?

Activity 30 – Super substructure

Original Budget = $2,000,000

Original Duration = 18 Weeks

Number of Weeks between Planned Start Date and Status State = ______ #Weeks to status date (From Question 1.

BCWS = #Weeks to status date / Original Duration * Original Budget

BCWS = ______________________________

Activity 50 – Interior

Original Budget = $1,800,000

Original Duration = 14 Weeks

Number of Weeks between Planned Start Date and Status State=_______ #Weeks to status date (From Question 1).

BCWS = #Weeks to status date / Original Duration * Original Budget

BCWS = ______________________________

Question 3 – Calculate the BCWP (Earned Value). This is based on the original budget and the actual work completed for the activities that are in progress. This calculation will provide the budgeted cost of the work completed to date.

Activity 30: Super Sub Structure

Original Budget: = $2,000,000

Actual Percent Complete = 75%

Earned Value = 75% * Original Budget _____________________

Activity 50: Interior

Original Budget = $1,800,000

Actual Percent Complete = 50%

Earned Value = 50% * Original Budget ______________________

Question 4 – Calculate the Schedule Performance Index (SPI) and the Cost Performance Index (CPI) based on BCWS and BCWP. Based on these calculations, determine if the project is ahead or behind schedule and if the cost is under or over budget?

SPI = BCWP / BCWS

CPI = BCWP / ACWP

Activity 30 = Super Substructure

SPI = _____________________

CPI = _____________________

Ahead or Behind Schedule? _____________________

Under or Over Budget? _____________________

Activity 50 = Interior

SPI = _____________________

CPI = _____________________

Ahead or Behind Schedule? _____________________

Under or Over Budget? _____________________

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Place Order” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order